Quarter 3/2017

Construction progress of Residences at Mandarin Oriental, Bangkok September 2017

By the end of September 2017 more than 52% of the work had been completed, with structural work, slip forming of columns and shear walls, floor slabs, and formwork outriggers finished up to level 36. Architectural work on the mockup room and internal walls of room units was carried out up to level 16. Mechanical and electrical work for room units was fully completed up to level 18.