Quarter 4/2017

Construction progress of Residences at Mandarin Oriental, Bangkok December 2017

At the end of December 2017 work is over 68% complete. Structural work and slip forming of columns and shear walls have been finished up to level 47. Floor slabs are completed up to level 45 and installation of formwork floor slabs up to level 46. For architectural work, room units' internal walls have been completed up to level 25. Mechanical and electrical work for room units is fully finished up to level 27.