Quarter 1/2018

Construction progress of The Residences at Mandarin Oriental, Bangkok March 2018

At the end of March 2018, work is over 80% complete. Structural work and slip forming of columns and shear walls have been finished up to the machine floor. Floor slabs are completed up to machine floor and installation of formwork floor slabs up to the machine floor. In architectural work, room unit internal walls have been completed up to level 38. Mechanical and electrical work for room units is fully finished up to level 35.